Microsoft and G42's planned $1 billion AI data center in Kenya has stalled amid disagreements over power commitments, with President William Ruto saying the country would need to " switch off half the country" to support the project at full scale . Tom's Hardware reports: The project, announced in May 2024 during Ruto's visit to Washington, was supposed to bring a geothermal-powered data center to the Olkaria region in Kenya's Rift Valley. G42 was to lead construction, with the facility running Microsoft Azure in a new East Africa cloud region. The first phase targeted 100 megawatts of capacity and was expected to be operational by this year, with a long-term goal of scaling to 1 gigawatt. President Ruto isn't exaggerating about shutting off half the country's power. Kenya's total installed electricity capacity sits between 3,000 and 3,200 megawatts, and peak demand reached a record 2,444 megawatts in January, according to data from KenGen, the country's government-owned electricity producer.…